Electrical Panel Board Final Inspection and Testing

Final Inspection and Testing

QCI Carry out ROUTINE TESTS as per IEC 60439-1 standards. The following minimum tests

must be performed:

Visual inspection test – Checking of the complete switchboard in accordance with IEC

60439-1 standards and approved drawings. Checking of Integrity of Wiring, Tightness of all

joints, and Torque test on all bus connections, etc.

Di-electric Test – Done using a MEGGER (verification of Insulation resistances between

phases, phase-neutral, phase-earth and neutral-earth). This test is also verified by a HIPOT

test using a 2.5kV test between phases for 1min.

Mass Continuity Test – To check if there is proper earth continuity from end of the

switchboard to the other. This test can be checked